Boiler Control System Retrofit

A phased modernization replaced an obsolete three-boiler control system while keeping the remaining boilers available to serve the plant.

Replacing an Obsolete Boiler-Control Platform

A Westinghouse boiler-control system installed in the mid-1980s could no longer meet current standards or energy-saving requirements at Naval Base Kitsap in Bremerton, Washington. Systems Interface joined Coburn Contractors and MacDonald-Miller to deliver the upgrade from design through installation, training, and commissioning.

A Phased Three-Boiler Retrofit

The project replaced hardware, software, control panels, servers, workstations, and control-room monitoring. Systems Interface used Rockwell Automation burner-management and combustion-control solutions for three boilers, each with two combination natural-gas and steam-atomized-oil burners.

The Plant Master controls were replaced first. Each boiler was then modernized individually while the other two remained operational and continued supplying steam to the plant.

Commissioning and Operator Handoff

After field wiring was rerouted, Systems Interface completed point-to-point verification before power was applied. The team then performed startup, commissioning, operator and maintenance training, documentation updates, and final system handoff.